Loop 202 Santan Freeway Improvements

Loop 202 Closure Map

Stay informed as the Arizona Department of Transportation (ADOT) makes improvements to the Loop 202 Santan Freeway. The project is scheduled for completion in 2027.

Major elements of the project include:

  • Add two lanes in each direction between Price Rd. and Gilbert Rd.
  • Add one lane in each direction between Gilbert Rd. and Val Vista Dr.
  • Widen Loop 202 freeway entrance and exit ramps
  • Widen bridges over Arizona Ave., Union Pacific Railroad and Consolidated Canal

Each of the freeway entrance and exit ramps will close for up to 60 consecutive days to widen the ramps. ADOT will stagger this work to avoid closing consecutive freeway entrance or exit ramps in the same direction. Ramps connecting the Loop 101 and Loop 202 freeways also will close for up to 15 consecutive days as improvements are made. 

Traffic Restrictions

Loop 202

  • Eastbound Loop 202 will be narrowed to two lanes between Alma School Road and Arizona Avenue from 10 p.m. Friday, March 20, until 10 a.m. Saturday, March 21, and again from 8 p.m. Saturday, March 21, until 10 a.m. Sunday, March 22.
  • Eastbound Loop 202 will be closed between Price Road and Arizona Avenue from 10 p.m. Friday, April 3, until 5 a.m. Monday, April 6. The ramps connecting Loop 101 south to Loop 202 east will be closed. 

At Alma School Road:

  • Eastbound Loop 202 exit ramp at Alma School Road is closed for reconstruction until early April.

At Arizona Avenue:

  • Westbound Loop 202 exit ramp at Arizona Avenue is closed for reconstruction until late April.
  • Northbound Arizona Avenue will be narrowed to two lanes between Willis and Pecos roads from 8:30 a.m. Monday, March 16, until 5 p.m. Friday, April 3.
  • Eastbound Loop 202 entrance ramp at Arizona Avenue will be closed nightly from 9 p.m. until 5 a.m. starting Monday night, March 23, and ending Wednesday morning, March 25. 

At McQueen Road:

  • Eastbound Loop 202 entrance ramp at McQueen Road is closed for reconstruction until mid-May.
  • Westbound Loop 202 exit ramp at McQueen Road will be closed from 10 p.m. Friday, April 3, until 5 a.m. Saturday, April 4.

At Cooper Road:

  • Eastbound Loop 202 exit ramp at Cooper Road is closed for reconstruction until late May.
  • Westbound Loop 202 entrance ramp at Cooper Road will be closed from 10 p.m. Friday, April 3, until 5 a.m. Saturday, April 4. 

Contact ADOT

Contact Chandler’s Construction Liaison

Chandler is supplementing ADOT’s community outreach efforts to assist residents and businesses in obtaining information and addressing questions about the project. For questions or further information related to this project, please contact us.

Project Hotline: 480-898-4060