Water Main Replacements

Water Main Replacements Project

Tyson Manor, Sunset Manor, Galveston Street, and Erie Street Water Main Replacements Project (WA2203.401)

Construction is nearing completion for the City of Chandler's water main replacement project which will replace water pipeline, associated residential service connections, and fire hydrants in Erie Street, Sunset Manor, and Tyson Manor. Fire hydrants will also be installed in Hartford Street between Chandler Boulevard and Erie Street. A future phase of the water main replacement project will take place in Arrowhead Meadows neighborhood. These neighborhoods are located north of Chandler Boulevard to Galveston Street, between Alma School Road and Hartford Street, and portions of the project include relocating the waterline from the alley behind the residences to the street in front of the residences.

Chandler selected Achen-Gardner Construction to construct these improvements which will take place in phases (see graphic) with the following tentative schedule (subject to change). Completion is expected by the end of 2025:

  • Phase 1:  Erie Street & Alma School – late May thru late July 2025
  • Phase 2:  Sunset Manor – mid-May thru mid-October 2025
  • Phase 3:  Galveston Street – late September thru early October (school’s Fall Break)
  • Phase 4:  Tyson Manor – late September thru mid-December 2025

Current Construction Information (March 5, 2026):

  • Water main installation and associated service replacements are complete, and crews are finalizing restoration in work areas.
  • As part of the completion of the project, the contractor is in the area visiting residents on both weekdays and Saturdays to obtain sign offs on the warranty letters related to work on private properties.
  • Currently scheduled to take place weekdays, March 9 – 23, crews will apply an asphalt slurry seal treatment, as necessary, in various locations throughout the project area. Traffic will be shifted away from the work areas. On-street parking may be restricted, and No Parking signs will be placed in advance of the work.  Access will be maintained to the extent possible but there will be delays as work crosses side streets and driveways. Impacted residents will receive a door hanger in advance of this work. 

Resident and business access is being maintained during this work although it may not be the most direct route. On-street parking may not be permitted with "No Parking" signs posted in advance, where necessary to accommodate the work effort.

If you have questions or need additional information regarding the project, please contact us.

Project Hotline: 480-898-4060