Tyson Manor, Sunset Manor, Galveston Street, and Erie Street Water Main Replacements Project (WA2203.401)
Construction began in May for the City of Chandler's water main replacement project which will replace water pipeline, associated residential service connections, and fire hydrants in Erie Street, Sunset Manor, and Tyson Manor. Fire hydrants will also be installed in Hartford Street between Chandler Boulevard and Erie Street. A future phase of the water main replacement project will take place in Arrowhead Meadows neighborhood. These neighborhoods are located north of Chandler Boulevard to Galveston Street, between Alma School Road and Hartford Street, and portions of the project include relocating the waterline from the alley behind the residences to the street in front of the residences.
Chandler selected Achen-Gardner Construction to construct these improvements which will take place in phases (see graphic) with the following tentative schedule (subject to change). Completion is expected by the end of 2025:
- Phase 1: Erie Street & Alma School – late May thru late July 2025
- Phase 2: Sunset Manor – mid-May thru mid-October 2025
- Phase 3: Galveston Street – late September thru early October (school’s Fall Break)
- Phase 4: Tyson Manor – late September thru mid-December 2025
Current Construction Information (Dec. 19, 2025):
- Crews are working to complete installation of the final remaining residential services throughout the project area. Tie-overs are being coordinated with the respective property owners or residents via door hanger or other contact.
- Crews are currently conducting asphalt, concrete and landscape restoration in various areas and are scheduled to remove any unnecessary traffic control prior to Christmas.
- Scheduled to continue into January, crews will work to conduct final clean up and address any remaining punch list items. This may require short-term, intermittent traffic restrictions localized to the activity.
- Expected to take place in March 2026 when warmer weather returns, crews will return to apply slurry seal to streets, as necessary.
Crews will not be working Dec. 25 - 28 and Jan. 1 - 4 in observance of the holidays. On behalf of the entire project team, we wish you and yours a very Happy Holiday and as this project nears completion, we thank you for your patience during construction.
Resident and business access is being maintained during this work although it may not be the most direct route. On-street parking may not be permitted with "No Parking" signs posted in advance, where necessary to accommodate the work effort.
If you have questions or need additional information regarding the project, please contact us.



