Sewer Manhole & Pipeline Rehab Projects

The following sewer pipeline, manhole, and lift station rehabilitation are scheduled. Detailed construction and schedule information on each project is provided below:

  • Price Road: Loop 202 Santan Fwy to Queen Creek Road
  • Chandler Lift Stations Rehabilitation
  • Delaware Street & Erie Street Wastewater Infrastructure Improvements
Price Road Sewer Pipeline Rehabilitation (Loop 202 Santan Fwy to Queen Creek Road)
Price Road Sewer Rehab Project Area

The City of Chandler has contracted with B&F Contracting to rehabilitate the sewer pipeline in Price Road, from just south of the Loop 202 Santan Fwy to Queen Creek Road, and then further south slightly to the Ocotillo Water Reclamation Facility (OWRF) at the southwest corner of Price Rd and Queen Creek Rd. The “trenchless” technology of lining the sewer pipeline extends the life of the sewer pipeline and is less impactful and of shorter duration than removal and replacement.

  • Work to line the existing sewer pipeline and rehabilitate or construct manholes is nearing completion.
  • The sewer bypass was shut down and taken out of operation on Tuesday, Oct. 14.  
  • Scheduled to take place through the week of Oct. 20, bypass pipe will be removed from west of Price Road, south of Germann Road to Queen Creek Road, with landscape restoration to follow.
  • Scheduled to take place Oct. 21 - 31, bypass pipe will be removed from the Queen Creek intersection and also from the Willis Road intersection.
  • Scheduled to take place Nov. 1 through the end of the year, the remainder of the bypass pipe will be removed from the project, with pavement or landscape restoration to follow. Removal of bypass pipe in Price Road will require lane and possible turn restrictions, so please obey traffic signage as it is placed for the safety of travelers and contractor crews. 

During construction, roads will remain open for travel with lane reductions and possible turn restrictions in place. Night work may be required for work in Price Road nearest Loop 202 Santan Freeway.  (WW2302.401)

ADOT is currently working on a project near this area to widen the Loop 202 Santan Freeway. For more information, visit Loop 202

For questions or further information related to this work, please contact us.

Project Hotline: 480-898-4060 

Sewer Lift Station Rehabilitation Project

The City of Chandler has contracted with MGC Contractors to rehabilitate several wastewater lift stations throughout Chandler to make repairs or upgrades. Work will typically take place on-site at the lift station; however, traffic restrictions may be needed in some instances to accommodate the work activity as many of these sites have limited space available. Work will typically take place during daytime hours, weekdays (excluding major holidays).  A map of the planned locations and current tentative schedule is provided. 

Chandler Lift Station Location Map
Chandler Lift Station Schedule

For questions or further information related to this work, please contact us.

Project Hotline: 480-898-4060

The City of Chandler has contracted with B&F Contracting to conduct various activities related to Chandler’s wastewater infrastructure in the area between Arizona Avenue and Hamilton Street, from Chandler Boulevard to Galveston Street.

Work began in late September and includes documenting existing conditions to identify locations where there may be a need for localized repairs or rehabilitation (lining) of the existing pipeline. Some processes include the need for a sewer bypass, which diverts flows from the existing pipeline underground to an above-ground pipe which is installed from one manhole to another. This type of rehabilitation minimizes impacts as crews clean and line the existing sewer pipeline without having to trench excavate.

Work west of Delaware Street will primarily take place in the alleyway, where the sewer pipeline is located, so alleys or segments of alleys may be closed to accommodate this work. Work in the road may require short road closures, or restrictions of lanes or on-street parking. Signage will be placed in advance to direct travelers. Work will take place primarily during daytime hours, weekdays, with traffic control remaining in place 24/7 to protect the work zone. 

Project completion is expected in late 2025. Thank you for your patience during this work.