The following sewer pipeline, manhole, and lift station rehabilitation are scheduled. Detailed construction and schedule information on each project is provided below:
- Price Road: Loop 202 Santan Fwy to Queen Creek Road
- Chandler Lift Stations Rehabilitation

The City of Chandler has contracted with B&F Contracting to rehabilitate the sewer pipeline in Price Road, from just south of the Loop 202 Santan Fwy to Queen Creek Road, and then further south slightly to the Ocotillo Water Reclamation Facility (OWRF) at the southwest corner of Price Rd and Queen Creek Rd. The “trenchless” technology of lining the sewer pipeline extends the life of the sewer pipeline and is less impactful and of shorter duration than removal and replacement.
Bypass Installation: Installation of the sewer bypass is complete, and an important part of the rehabilitation process in order to bypass wastewater flows from the existing sewer pipeline to nearby manholes so that work can take place in the existing pipeline.
The bypass pipe has been buried below the asphalt surface in Price Road to better accommodate travel during the sewer pipeline rehabilitation process. Please note that this asphalt application is temporary in nature to accommodate protecting the bypass pipe beneath the road surface, but also permitting travel on the roadway. Late this year, after pipeline rehabilitation is complete, the asphalt and bypass pipes will be removed, and permanent restoration of asphalt will take place.
The bypass has been put into operation and is being monitored 24/7 during operation.
Sewer Manhole Rehabilitation: Crews are working at various locations along Price Road to install new or rehabilitate existing manholes, which requires lane reductions and possible turn restrictions in Price Road to shift traffic away from the work area.
Crews continue work to rehabilitate manholes in Price Road with work at the Continuum intersection, and also south of the Germann intersection, taking place through the end of next week.
Scheduled to begin the week of August 11, manhole rehabilitation will take place in the Germann intersection, and scheduled to begin the week of August 25, manhole rehabilitation will take place in Price Road, just north of Innovation. These activities are expected to take approximately 2-3 weeks each to complete. To accommodate this work, traffic will be shifted away from the work activity with possible left turn restrictions in place, in the interest of safety.
Sewer Pipeline Rehabilitation (Pipe Lining): Sewer pipeline rehabilitation (pipe lining) has begun with lining completed in Price Road north of Willis Road, and currently taking place from approximately Willis Road to Armstrong Place. The lining process will continue in Price Road between manholes, in approximate one-half mile segments, moving in a southerly direction to south of Queen Creek Road.
Scheduled through the end of July, pipe lining activity will take place between Willis Road and Germann Road, and scheduled for the month of August, pipe lining activity will take place between Germann Road and Queen Creek Road. This effort includes stationing equipment at various manhole locations to insert a lining in the existing sewer pipeline, which is then cured to create a permanent lining within the pipe.
Please note that the lining and curing process is a 24/7 operation taking place during daytime hours into evening and night hours based on the length of the lining and curing process. Night work may be required for work in Price Road nearest Loop 202 Santan Freeway. As sewer rehabilitation completes in late 2025, the bypass removal and restoration will begin, with project completion scheduled for February 2026.
During construction, roads will remain open for travel with lane reductions and possible turn restrictions in place. Night work may be required for work in Price Road nearest Loop 202 Santan Freeway. (WW2302.401)
ADOT is currently working on a project near this area to widen the Loop 202 Santan Freeway. For more information, visit Loop 202.
For questions or further information related to this work, please contact us.
Project Hotline: 480-898-4060
The City of Chandler has contracted with MGC Contractors to rehabilitate several wastewater lift stations throughout Chandler to make repairs or upgrades. Work will typically take place on-site at the lift station; however, traffic restrictions may be needed in some instances to accommodate the work activity as many of these sites have limited space available. Work will typically take place during daytime hours, weekdays (excluding major holidays). A map of the planned locations and current tentative schedule is provided.


For questions or further information related to this work, please contact us.
Project Hotline: 480-898-4060