The following sewer pipeline, manhole, and lift station rehabilitation are scheduled. Detailed construction and schedule information on each project is provided below:
- Price Road: Loop 202 Santan Fwy to Queen Creek Road
- Chandler Lift Stations Rehabilitation
- Delaware Street & Erie Street Wastewater Infrastructure Improvements
The City of Chandler has contracted with B&F Contracting to rehabilitate the sewer pipeline in Price Road, from just south of the Loop 202 Santan Fwy to Queen Creek Road, and then further south slightly to the Ocotillo Water Reclamation Facility (OWRF) at the southwest corner of Price Rd and Queen Creek Rd. The “trenchless” technology of lining the sewer pipeline extends the life of the sewer pipeline and is less impactful and of shorter duration than removal and replacement.
Work to line the existing sewer pipeline and rehabilitate or construct manholes is complete with crews working to remove the sewer bypass which was put in place prior to the project to facilitate the planned work.
Bypass removal has been completed, and crews have begun work to conduct restoration:
- Crews continue work on lateral lines near Queen Creek Road through Feb. 9
- Scheduled to take place beginning the week of Feb. 9, crews will work on manholes in the northbound lanes of Price Road, at the Willis, Armstrong and Spectrum intersections for 1-2 weeks.
- Scheduled for mid to late February, remaining landscaping will take place and any other restoration, as well as the striping of Price Road.
- As a follow-on effort to the project, scheduled for sometime in April, a slurry seal pavement application will take place and final striping applied.
(WW2302.401)
ADOT is currently working on a project near this area to widen the Loop 202 Santan Freeway. For more information, visit Loop 202.
For questions or further information related to this work, please contact us.
Project Hotline: 480-898-4060
The City of Chandler has contracted with MGC Contractors to rehabilitate several wastewater lift stations throughout Chandler to make repairs or upgrades. Work will typically take place on-site at the lift station; however, traffic restrictions may be needed in some instances to accommodate the work activity as many of these sites have limited space available. Work will typically take place during daytime hours, weekdays (excluding major holidays). A map of the planned locations and current tentative schedule is provided.
For questions or further information related to this work, please contact us.
Project Hotline: 480-898-4060
The City of Chandler has contracted with B&F Contracting to conduct various activities related to Chandler’s wastewater infrastructure in the area between Arizona Avenue and Hamilton Street, from Chandler Boulevard to Galveston Street.
Work includes documenting existing conditions to identify locations where there may be a need for localized repairs or rehabilitation (lining) of the existing pipeline. Some processes include the need for a sewer bypass, which diverts flows from the existing pipeline underground to an above-ground pipe which is installed from one manhole to another. This type of rehabilitation minimizes impacts as crews clean and line the existing sewer pipeline without having to trench excavate.
Work west of Delaware Street will primarily take place in the alleyway, where the sewer pipeline is located, so alleys or segments of alleys may be closed to accommodate this work. Work in the road may require short road closures, or restrictions of lanes or on-street parking. Signage will be placed in advance to direct travelers. Work will take place primarily during daytime hours, weekdays, with traffic control remaining in place 24/7 to protect the work zone.
Project completion is expected in early 2026. Thank you for your patience during this work.



