Sewer Manhole & Pipeline Rehab Projects

The following sewer pipeline, manhole, and lift station rehabilitation are scheduled. Detailed construction and schedule information on each project is provided below:

  • Price Road: Loop 202 Santan Fwy to Queen Creek Road
  • Price Road: Frye Road to Elliot Road
  • Chandler Boulevard and 56th Street: 56th Street from Frye to Pecos
  • Chandler Lift Stations Rehabilitation
Price Road Sewer Pipeline Rehabilitation (Loop 202 Santan Fwy to Queen Creek Road)
Price Road Sewer Rehab Project Area

The City of Chandler has contracted with B&F Contracting to rehabilitate the sewer pipeline in Price Road, from just south of the Loop 202 Santan Fwy to Queen Creek Road, and then further south slightly to the Ocotillo Water Reclamation Facility (OWRF) at the southwest corner of Price Rd and Queen Creek Rd. The “trenchless” technology of lining the sewer pipeline extends the life of the sewer pipeline and is less impactful and of shorter duration than removal and replacement.

Bypass Installation: Crews will soon begin installation of a sewer bypass to bypass wastewater flows from the existing sewer pipeline to nearby manholes for work to take place in the existing pipeline. This work will initially take place off the roadway as crews fuse together pipe, and in August, lane reductions will begin on Price Road for bypass installation along Price Road. The sewer bypass will generally be installed just below the road surface, with some exceptions, from the Loop 202 to Germann Road, and also across Queen Creek Road. There may be brief restrictions as this work takes place across side streets or driveways. Once put into operation, the bypass will be monitored 24/7 for the sewer rehabilitation process to begin.

Sewer Rehabilitation (Pipe Lining): Scheduled to begin in December 2024, the sewer rehabilitation process will begin. This effort includes stationing equipment at various manhole locations to clean and then insert a lining in the existing sewer pipeline, which is then cured to create a permanent lining within the pipe. In addition, several manholes along the alignment require full replacement.

Work will primarily take place during daytime hours; however, once the lining curing process begins, it may run into evening or night hours based on the length of the lining and curing process. As sewer rehabilitation completes in late 2025, the bypass removal and restoration will begin with project completion scheduled for February 2026.

During construction, roads will remain open for travel with lane reductions and possible turn restrictions in place. Night work may be required for work in Price Road nearest Loop 202 Santan Freeway. (WW2302.401)

For questions or further information related to this work, please contact us.

Project Hotline: 480-898-4060 

Price Road Sewer Pipeline Rehabilitation (Frye Road to Elliot Road)

The City of Chandler has contracted with B&F Contracting to rehabilitate the sewer pipeline in Price Road, from south of Frye Road to Elliot Roa. The “trenchless” technology of lining the sewer pipeline extends the life of the sewer pipeline and is less impactful and of shorter duration than removal and replacement.

Sewer bypass pipe is currently being removed from the area in Chandler Blvd south to Frye Rd to be relocated north for rehabilitation to take place near Ray Rd. The bypass should be completely removed by mid to late August. Scheduled to take place July 17 - 19, the northbound Price Rd frontage road will be closed just north of the Lowe's plaza entrance for paving and adjustments as part of the bypass removal process. 

Price Road Sewer Rehab Project Area

Scheduled to begin in mid-July, crews will install sewer bypass pipe to be able to bypass wastewater flows from the existing sewer pipeline to nearby manholes for work to take place in the existing pipeline. As part of the bypass set-up, which primarily is above ground typically along the curb line, crews will sawcut locations where vehicle crossings take place, such as driveways and side streets, to bury the bypass pipe at those locations to be able to permit traffic to cross. There may be brief restrictions at the driveway/side street as this work takes place, but crews will work during night hours in high traffic crossing areas to minimize the impact to travelers and businesses. In addition, to minimize restrictions in Price Road, the bypass will be set along nearby side streets of Mission Park Road, Coronado Street and Linda Lane. The bypass is expected to take about 4-6 weeks to install.

Scheduled for early September 2024, crews will begin the sewer rehab (pipe lining) process in Price Rd. This effort will include stationing equipment at various manhole locations to clean and then insert a lining in the existing sewer pipeline, which is then cured to create a permanent lining within the pipe.

Roads will remain open for travel during this work with traffic shifted away from the work area, and lane and possible turn restrictions in place, as needed. Work will primarily take place during daytime hours; however, once the lining curing process begins, it may run into evening or night hours based on the length of the lining and curing process. Once work is complete in all areas, the sewer bypass will be removed, and restoration will take place. Project completion is scheduled for late Fall 2024. (WW2210.401)

For questions or further information related to this work, please contact us. 

Project Hotline: 480-898-4060 

Sewer Manhole Rehabilitation Project
Chandler Blvd-56th St Sewer Rehab Project Area

The City of Chandler has contracted with FPS Civil to rehabilitate sewer manholes in Chandler Blvd, from west of 54th St to Beck Ave, and in 56th St, from Chandler Blvd to Pecos Rd. Roads remain open for travel during work with lane and possible turn restrictions in place during work hours to shift traffic away from the work zone.

Crews are currently working to complete any punchlist items before final completion. Traffic control will be in place, as needed, at locations requiring repair work.

Access to residences and businesses will be maintained and thank you for your patience during this work. (WW2208.402)

For questions or further information related to this work, please contact us. 

Project Hotline: 480-898-4060 

Sewer Lift Station Rehabilitation Project

The City of Chandler has contracted with MGC Contractors to rehabilitate several wastewater lift stations throughout Chandler to make repairs or upgrades. Work will typically take place on-site at the lift station; however, traffic restrictions may be needed in some instances to accommodate the work activity as many of these sites have limited space available. Work will typically take place during daytime hours, weekdays (excluding major holidays).  A map of the planned locations and current tentative schedule is provided. 

Chandler Lift Station Location Map
Chandler Lift Station Schedule

For questions or further information related to this work, please contact us.

Project Hotline: 480-898-4060