Sewer Manhole & Pipeline Rehab Projects

The following sewer pipeline, manhole, and lift station rehabilitation are scheduled. Detailed construction and schedule information on each project is provided below:

  • Price Road: Loop 202 Santan Fwy to Queen Creek Road
  • Price Road: Frye Road to Elliot Road
  • Chandler Boulevard and 56th Street: 56th Street from Frye to Pecos
  • Chandler Lift Stations Rehabilitation
Price Road Sewer Pipeline Rehabilitation (Loop 202 Santan Fwy to Queen Creek Road)
Price Road: Loop 202 Santan Freeway to Queen Creek Road

The City of Chandler has contracted with B&F Contracting to rehabilitate the sewer pipeline in Price Road, from just south of the Loop 202 Santan Fwy to Queen Creek Road, and then further south slightly to the Ocotillo Water Reclamation Facility (OWRF) at the southwest corner of Price Rd and Queen Creek Rd. The “trenchless” technology of lining the sewer pipeline extends the life of the sewer pipeline and is less impactful and of shorter duration than removal and replacement.

Construction is not scheduled to begin until June 2024 with sewer bypass set-up taking place to prepare for the lining process.

During construction, roads will remain open for travel with lane reductions and possible turn restrictions in place. Night work may be required for work in Price Road nearest Loop 202 Santan Freeway. (WW2302.401)

For questions or further information related to this work, please contact us.

Project Hotline: 480-898-4060 

Price Road Sewer Pipeline Rehabilitation (Frye Road to Elliot Road)

The City of Chandler has contracted with B&F Contracting to rehabilitate the sewer pipeline in Price Road, from south of Frye Road to Elliot Roa. The “trenchless” technology of lining the sewer pipeline extends the life of the sewer pipeline and is less impactful and of shorter duration than removal and replacement.

Price Road Sewer Rehab Project Area

Crews have completed installation of the sewer bypass pipe and are currently bypassing wastewater flows from the existing sewer pipeline to nearby manholes. The sewer rehabilitation (pipe lining) process is beginning in Price Road. This effort includes stationing equipment at various manhole locations to clean and then insert a lining in the existing sewer pipeline, which is then cured to create a permanent lining within the pipe.  

Northbound Price Road is currently closed just north of Chandler Boulevard, and north of the entrance to the Lowe's plaza while crews line the sewer pipeline in this area. This road is expected to be reopened late Friday, May 24.
 
Crews are currently working in manholes in the Chandler Boulevard median, east of Price Road. To accommodate this work, traffic is shifted away from the median in this area.
 
Scheduled to take place May 28 – June 21, lane reductions will be in place for southbound Price Road traffic at Chandler Boulevard, still allowing left turns, right turns, and one thru southbound lane at Chandler Boulevard. These restrictions are necessary to facilitate work in manholes in the Chandler Boulevard/Price Road intersection on the west side of the Loop 101. 
 
Scheduled to begin May 28 for approximately two weeks, crews will work to rehabilitate sewer pipeline in northbound Price Road, south of Chandler Boulevard. Price Road will remain open for travel with lane reductions in place to shift traffic away from the work area.
 

Unless noted, roads will remain open for travel during this work with traffic shifted away from the work area, and lane and possible turn restrictions in place, as needed. Work will primarily take place during daytime hours; however, the lining curing process may run into evening or night hours based on the length of the lining and time needed for the curing process. Once work is complete in all areas, the sewer bypass will be removed, and restoration will take place. Project completion is scheduled for Fall 2024. (WW2210.401)

For questions or further information related to this work, please contact us. 

Project Hotline: 480-898-4060 

Sewer Manhole Rehabilitation Project

The City of Chandler has contracted with FPS Civil to rehabilitate sewer manholes in Chandler Boulevard

Chandler Blvd-56th St Sewer Rehab Project Area

and 56th Street, and 56th Street from Frye to Pecos. Work at each sewer manhole is expected to take about 1-2 weeks. Crews will work in Chandler Boulevard, from west of 54th Street to Beck Avenue, and in 56th Street from Chandler Boulevard to Pecos Road. Work began in 56th Street, south of Chandler Boulevard, to access and rehabilitate manholes and is moving in a northerly direction. Roads remain open for travel during work with lane and possible turn restrictions in place during daytime work hours to shift traffic away from the work zone. Traffic control will be removed during off-work hours to restore the road to normal travel. Work will take place weekdays, typically during daytime hours, with night work planned for the Chandler Boulevard/56th Street intersection. Work is expected to be complete in June 2024. (WW2208.402)

Access to residences and businesses will be maintained and thank you for your patience during this work.

For questions or further information related to this work, please contact us. 

Project Hotline: 480-898-4060 

Sewer Lift Station Rehabilitation Project

The City of Chandler has contracted with MGC Contractors to rehabilitate several wastewater lift stations throughout Chandler to make repairs or upgrades. Work will typically take place on-site at the lift station; however, traffic restrictions may be needed in some instances to accommodate the work activity as many of these sites have limited space available. Work will typically take place during daytime hours, weekdays (excluding major holidays).  A map of the planned locations and current tentative schedule is provided. 

Chandler Lift Station Location Map
Chandler Lift Station Schedule

For questions or further information related to this work, please contact us.

Project Hotline: 480-898-4060