Downtown Improvements

Downtown Chandler Improvements Projects (ST2203.101)

Downtown Chandler Improvement Project Map

The City of Chandler is currently in construction for three important projects for improvements to Downtown Chandler.

  • Wall Street Improvements
  • Boston Street Reconstruction
  • Chandler City Hall Parking Lot & Alley Improvements

Work is taking place in the summer/fall 2024 timeframe to be complete prior to Downtown Chandler’s peak season.

The following information is provided related to project components and schedule for each of the three projects.

The City of Chandler recently completed design for aesthetic and pedestrian improvements along Wall Street between Chicago Street and Frye Road. As part of the ongoing revitalization south of the Historic Square, Wall Street Improvements (from Chicago Street to Frye Road) will improve and increase pedestrian spaces in Downtown Chandler. Renderings of the planned improvements are provided below.

Crews are scheduled to pave back Phase 1 on Monday, July 29, and beginning Tuesday, July 30, work will shift to Phase 2 (north half of Wall Street). Crews will work in the north half of Wall Street to conduct removals and reconstruct this area. Following this work, crews will install final signage, planters, irrigation, and lighting.

Access is being maintained from Arizona Avenue to the parking area, and pedestrian access to Wall Street will be maintained during construction. Work is taking place during daytime hours, weekdays, excluding major holidays, and accommodations made for sanitation and deliveries. Work areas will be secured to provide pedestrian access during off-work hours and weekends. 

Wall Street Improvements Phasing

 

Wall Street Daytime Image:

Wall Street - Daytime Image

 

Wall Street Night Image: 

Wall Street - Night Image

The City of Chandler has contracted with Sunland Asphalt to construct improvements to Boston Street, between San Marcos Place and California Street. Improvements include full asphalt and subsurface removal and replacement as well as widening sidewalks on the north side of Boston, east of Oregon Street, and on the south side of Boston, west of Oregon Street, with ADA (Americans with Disabilities Act) and pedestrian crosswalk improvements, and a ride share/drop off area. Construction began in early May and is expected to be complete in October 2024.

To accommodate Downtown Chandler visitors, this work is being conducted during the summer and has been phased to accommodate one-way traffic (eastbound only) on Boston Street, west of San Marcos Place. Work will be conducted one phase at a time with tentative dates provided (see graphic). 

Crews for the Boston Street Reconstruction Project continue work in Phase 5, with Boston Street closed to vehicular traffic from California to San Marcos through approximately August 15.  Detour signage is in place to direct travelers around the closure, and pedestrian access is being maintained during this time. Staff, patrons, and deliveries accessing the Oregon Street Parking garage may do so from the south, and those accessing the alley west of San Marcos Place may do so from the north.

Scheduled to take place Wednesday, July 24, paving will take place on Boston Street, with utility adjustments (for manholes and valves), striping, and signage installation scheduled for the week of July 29. Boston Street will remain closed as crews remove, reconstruct subsurface, and reinstall brick pavers in Boston Street, just west of San Marcos Place, which is expected to take 1-2 weeks to complete. 

In an effort to minimize the impacts to Downtown Chandler businesses, crews begin work at 3 a.m. each morning, working 9-hr days Monday through Thursday, and a 4-hr day on Fridays

Thank you for your patience during this work.

Boston Street Phasing

 

Chandler City Hall Parking lot will be removed and repaved with new striping and added lighting. In addition, the “alley” to the south of the Boston Street businesses (north of the City Hall parking lot) will be reconstructed and include installation of concrete curbing, valley gutter, trash enclosure and electric vehicle charging stations.

Crews are currently working to complete reconstruction of the City Hall parking area, with paving scheduled for Friday, July 26, and striping of the parking lot scheduled for Friday, August 2. The City Hall parking area will remain closed until striping is complete.

Scheduled for Thursday, July 25, fence will be set-up, but the gates and access remaining open, for the Boston Street alley, limited to the alley area from Serrano’s to Washington Street.  Scheduled for Monday, July 29, this area will be closed for the contractor to begin removals and the reconstruction of this area.  Access will be maintained from Arizona Avenue during this time.  Access will be provided, for deliveries only, to the alley just south of Boston Street until work begins in that area. Project completion is expected in October 2024.

 

City Hall Parking Lot Project Plan

For questions, concerns, or additional information, please email us or contact us.